Despite having 92% status of restored households in Typhoon Nina affected areas, Energy Secretary Alfonso G. Cusi directed the National Electrification Administration (NEA) and the involved electric cooperatives to complete restoration of power facilities as soon as possible.
The Secretary made the statement today upon learning about the latest report of Camarines Sur III Electric Cooperative’s (CASURECO III) slow movement in its restoration efforts.
“We cannot accept CASURECO III’s restoration status at 34% only following all of the combined efforts of the government and the private sector for restoring damages brought by Typhoon Nina,” Sec. Cusi emphasized.
Sec. Cusi underscored that “We want to determine the root cause of the delay in restoration, thus I wanted NEA through Admin. Ed Masongsong to take over the restoration efforts in CASURECO III covering Camarines Sur's Rinconada area.”
In a recent coordination efforts by the DOE, NEA Administrator Masongsong committed to create Task Force Rinconada to take over the restoration efforts in CASURECO III.
Sec. Cusi relayed that Admin. Masongsong already recalled the Project Manager and informed the Board of CASURECO III of the “NEA takeover" which will be implemented this February.
Other areas that the Secretary wanted to focus on are the hard-hit provinces of Catanduanes and Marinduque under the franchises of First Catanduanes Electric Cooperative (FICELCO) and Marinduque Electric Cooperative (MARELCO), respectively.
The Secretary made the statement today upon learning about the latest report of Camarines Sur III Electric Cooperative’s (CASURECO III) slow movement in its restoration efforts.
“We cannot accept CASURECO III’s restoration status at 34% only following all of the combined efforts of the government and the private sector for restoring damages brought by Typhoon Nina,” Sec. Cusi emphasized.
Sec. Cusi underscored that “We want to determine the root cause of the delay in restoration, thus I wanted NEA through Admin. Ed Masongsong to take over the restoration efforts in CASURECO III covering Camarines Sur's Rinconada area.”
In a recent coordination efforts by the DOE, NEA Administrator Masongsong committed to create Task Force Rinconada to take over the restoration efforts in CASURECO III.
Sec. Cusi relayed that Admin. Masongsong already recalled the Project Manager and informed the Board of CASURECO III of the “NEA takeover" which will be implemented this February.
Other areas that the Secretary wanted to focus on are the hard-hit provinces of Catanduanes and Marinduque under the franchises of First Catanduanes Electric Cooperative (FICELCO) and Marinduque Electric Cooperative (MARELCO), respectively.







Ross is known as the Pambansang Blogger ng Pilipinas - An Information and Communication Technology (ICT) Professional by profession and a Social Media Evangelist by heart.